S. 2035 · 109th Congress

A bill to extend the time required for construction of a hydroelectric project in the State of Idaho, and for other purposes.

Stage
Reported from committee
Introduced
2005-11-17
Latest action
2006-07-31 · Committee on Energy and Natural Resources. Reported by Senator Domenici with an amendment. With written report No. 109-304. Minority views filed.

Summary

Instructs the Federal Energy Regulatory Commission (FERC), upon licensee request, to: (1) extend the period for commencing construction of project works for FERC project number 4656 (Arrowrock Hydroelectric Project, Idaho) for a period of three years, if the project license is in effect on the date of the enactment of this Act; or (2) reinstate the license, if it has been terminated already, and extend for an additional three years the period for commencing such construction.