To extend the deadline for commencement of construction of a hydroelectric project involving the Gibson Dam.

Stage
Passed a chamber
Sponsor
Ryan Zinke
Introduced
2015-04-28
Latest action
2016-03-16 · Received in the Senate. Read twice. Placed on Senate Legislative Calendar under General Orders. Calendar No. 395.

Summary

(This measure has not been amended since it was introduced. The summary has been expanded because action occurred on the measure.)

(Sec. 1) This bill authorizes the Federal Energy Regulatory Commission to extend by six years the time period during which Gibson Dam Hydroelectric Company is required to commence construction on the Gibson Dam Hydroelectric Project located on the Sun River in Lewis, Clark, and Teton Counties, Montana.

The six-year time period starts upon expiration of the last extension.