H.R. 3447 · 114th Congress
To extend the deadline for commencement of construction of a hydroelectric project.
- Stage
- Passed a chamber
- Sponsor
- Virginia Foxx
- Introduced
- 2015-09-08
- Latest action
- 2016-03-16 · Received in the Senate. Read twice. Placed on Senate Legislative Calendar under General Orders. Calendar No. 396.
Summary
(Sec. 1) This bill authorizes the Federal Energy Regulatory Commission (FERC) to extend by six years the time period during which Wilkesboro Hydroelectric Company is required to commence construction on the W. Kerr Scott Hydropower Project located on the Yadkin River in Wilkes County, North Carolina.
In addition, FERC must reinstate the construction license if it is expired.